The cost of a 5 TPH CIP (Carbon-in-Pulp) gold processing plant depends heavily on the ore characteristics, gold recovery requirements, automation level, and whether you buy a complete turnkey plant or individual equipment. A realistic estimate is:
| Plant Type | Approximate Cost (USD) |
|---|---|
| Basic small-scale CIP plant (manual operation) | $300,000 – $600,000 |
| Standard 5 TPH CIP plant (complete equipment + installation) | $600,000 – $1,200,000 |
| High-standard turnkey CIP plant (automation, engineering, buildings) | $1,200,000 – $2,000,000+ |
A typical 5 TPH gold CIP plant usually falls around:
A complete plant normally contains:

Scopo:
Reduce raw ore from mine size to grinding size.
Typical equipment:
Estimated cost:
$80,000 – $200,000
Scopo:
Liberate gold particles from ore.
Equipment:
Estimated cost:
$150,000 – $350,000
Esempio:
5 TPH mulino a sfere:
This is the core gold recovery section.
Equipment:
Typical configuration:
Leach Tank 1
↓
Leach Tank 2
↓
CIP Tank 1
↓
CIP Tank 2
↓
CIP Tank 3
↓
Loaded Carbon
Estimated cost:
$150,000 – $350,000
Equipment:
Estimated cost:
$80,000 – $200,000
Equipment:
Estimated cost:
$50,000 – $200,000
ROM Gold Ore
↓
Vibrating Feeder
↓
Jaw Crusher
↓
Cone Crusher
↓
Fine Ore Bin
↓
Ball Mill
↓
Hydrocyclone
↓
Leaching Tanks
↓
CIP Tanks
↓
Carbon Adsorption
↓
Elution
↓
Electrowinning
↓
Gold Dore Bar
| Sezione | Costo stimato |
|---|---|
| Crushing system | $120,000 |
| Grinding system | $250,000 |
| Leaching + CIP tanks | $250,000 |
| Carbon recovery system | $100,000 |
| Eluizione ed elettroestrazione | $120,000 |
| Pumps, pipes, electrical | $100,000 |
| Installation & commissioning | $150,000 |
| Totale | ≈ $1 million |
Hard rock gold ore requires:
Cost may increase 20–50%.
Esempio:
Remote mine sites increase:
Manual plant:
Automatic plant:
For a 5 TPH CIP plant:
Assuming:
Annual throughput:
≈ 30,000 tons/year
Typical operating cost:
| Articolo | Costo |
|---|---|
| Potenza | $2–5/t |
| Lavoro | $1–5/t |
| Cyanide & chemicals | $3–10/t |
| Manutenzione | $2–5/t |
| Altro | $1–5/t |
Total:
≈ $10–30 per ton of ore
The investment changes greatly depending on the ore. To estimate more accurately, I would need:
Per un 5 TPH hard-rock gold CIP plant, a practical budget is usually around $800,000–$1.2 million USD.